勁松三(san)路(lu)(lu)(lu)站(zhan)是青(qing)島地鐵(tie)4號線自西(xi)向東敷(fu)設線路(lu)(lu)(lu)上(shang)的(de)一座明挖(wa)車站(zhan),位于遼陽西(xi)路(lu)(lu)(lu)南側,占路(lu)(lu)(lu)明挖(wa)法施工,站(zhan)位所處遼陽西(xi)路(lu)(lu)(lu)與勁松三(san)路(lu)(lu)(lu)交叉口(kou),交通(tong)量大(da),前期工作開展難度(du)大(da)、施工任務重(zhong)。由(you)于采用明挖(wa)法施工,基坑(keng)范圍內涉及(ji)自來水、燃氣(qi)、通(tong)信、電力、熱(re)力等多(duo)種市(shi)政管線,遷改難度(du)極大(da),管遷施工必須充分考慮周(zhou)邊車輛(liang)、行人(ren)通(tong)行及(ji)環保要求,盡量將施工對周(zhou)邊環境的(de)影(ying)響(xiang)降到最低(di)。
四號線公(gong)司工(gong)程(cheng)管(guan)理處(chu)會同集(ji)團工(gong)程(cheng)管(guan)理部(bu)、積極與公(gong)安交(jiao)警(jing)支隊、市(shi)(shi)城管(guan)局、交(jiao)警(jing)市(shi)(shi)北(bei)區大隊、市(shi)(shi)北(bei)區城管(guan)局、管(guan)線相關產權單位(wei)對接,制定(ding)合(he)理施(shi)(shi)工(gong)方(fang)案及交(jiao)通、人(ren)流疏導(dao)方(fang)案,經過(guo)(guo)細心(xin)籌劃、周密(mi)籌備、精心(xin)組織(zhi),勁松三路站(zhan)一期管(guan)線遷改(gai)與2018年2月初(chu)正(zheng)式啟動(dong)。并(bing)在(zai)施(shi)(shi)工(gong)過(guo)(guo)程(cheng)中采(cai)取夜間集(ji)中快速突(tu)擊、分(fen)幅分(fen)車道(dao)(dao)占用道(dao)(dao)路、次日立(li)即(ji)恢復瀝青路面等措施(shi)(shi),在(zai)基本不(bu)影響(xiang)(xiang)交(jiao)通及周邊居民的情況下(xia),開(kai)展管(guan)線遷改(gai)施(shi)(shi)工(gong)。同時,為(wei)了(le)順利(li)(li)實施(shi)(shi)熱(re)(re)(re)力管(guan)線割(ge)(ge)(ge)接工(gong)作,積極對接設計,優化管(guan)線割(ge)(ge)(ge)接方(fang)案及熱(re)(re)(re)力管(guan)線接頭設計,順利(li)(li)在(zai)供(gong)熱(re)(re)(re)季到來(lai)前完成了(le)管(guan)線接頭預埋施(shi)(shi)工(gong),為(wei)后(hou)期供(gong)熱(re)(re)(re)期間管(guan)線割(ge)(ge)(ge)接奠定(ding)基礎,可以在(zai)不(bu)影響(xiang)(xiang)居民供(gong)熱(re)(re)(re)的情況下(xia),完成管(guan)線遷改(gai)施(shi)(shi)工(gong);同時,優化了(le)自來(lai)水(shui)(shui)管(guan)線遷改(gai)方(fang)案,一期二(er)期管(guan)遷集(ji)中停水(shui)(shui),預埋管(guan)線接頭,即(ji)方(fang)便了(le)現(xian)場施(shi)(shi)工(gong),又減少了(le)停水(shui)(shui)次數(shu),將(jiang)施(shi)(shi)工(gong)對居民的影響(xiang)(xiang)降到了(le)最低。
勁松三路站(zhan)一期管遷施(shi)工(gong)(gong)(gong)經過(guo)了漫(man)長的施(shi)工(gong)(gong)(gong)期,克服(fu)了重(zhong)重(zhong)困難,終(zhong)于于11月22日全(quan)部(bu)完成,目前車站(zhan)已正式(shi)啟動土(tu)方開(kai)挖作業(ye),并著(zhu)手(shou)開(kai)展二期管遷及(ji)調流施(shi)工(gong)(gong)(gong),二期管遷及(ji)調流施(shi)工(gong)(gong)(gong)將(jiang)(jiang)對(dui)4號(hao)線TBM吊(diao)出井施(shi)工(gong)(gong)(gong)產(chan)生重(zhong)要(yao)影響,將(jiang)(jiang)面(mian)臨(lin)更加(jia)艱(jian)巨的任務,四號(hao)線公司將(jiang)(jiang)繼續全(quan)力推進。
車站土方開挖↑
自來水管(guan)線割接↓
- 青島市地鐵規劃設計院有限公司 2021年第二次社會招聘公告 2022-05-24
- 青島市地鐵規劃設計院有限公司 2021年第一次社會招聘公告 2022-02-25
- 戰“疫”復工在行動益群公司進一步完善地鐵大廈疫情防控措施 2021-03-09
- 青島地鐵集團成功舉辦 2號線車輛基地高壓觸電事故應急演練 2017-01-27
- 青島地鐵工程建設安全質量隱患排查系統正式上線試運行 2017-01-27